top of page

Power Transformer Refurbishment

In order to extend the life of AURIZON's ageing infrastructure, QENCOM were engaged to refurbish 11 critical 30MVA power transformers on their Blackwater Network. These assets were reconditioned for less than 10% of the replacement costs achieving improved reliability, at a small fraction of the CAPEX.

These works were completed on time, on budget in live operational infrastructure without incident.

These works included:

- Testing and Condition Assessments

- Disassembly and Relocation

- Cleaning of the Power Transformer
- Disassembly of Power Transformer
- Reassembly of the Power Transformer
- Oil Filling and Reprocessing

- Replacement of Equipment
- Painting of the Power Transformer
- Testing and Commissioning

bottom of page